Appalachia Has 5 Percent of Its States’ Data Center Power. It Is in Line for at Least 22 Percent of What Comes Next
A county-by-county check of public trackers finds the boom landing on three states, one power grid and a string of old energy sites. The power demand total equals the output of 29 nuclear reactors.
By Jim Branscome
The national story about data centers is that they are leaving the suburbs for the countryside and headed to Appalachia for the water and power, as I outlined in DailyYonder in January, https://dailyyonder.com/the-data-center-rush-in-appalachia/2026/01/07/.
Pew Research Center put numbers on it in April. Working from the industry database Data Center Map, Pew found that 87 percent of the data centers now operating in the United States are in urban areas. Of those being planned, 67 percent are in rural ones.
Nearly four in 10 planned facilities are headed for counties that have none today.
I wanted to know what that shift looks like in Appalachia. I run a daily aggregator of Appalachian news. A year ago a data center story turned up every week or two. Now there are dozens a day. (Subscribe free here: https://jbranx.github.io/Appalachian-News-Aggregator/. News gathered from about fifty Appalachian news sites delivered seven days a week. Free always.)
But nobody publishes a number for the region. The firms that track these projects sort them by state and by metro market, and Appalachia is neither. While using these public trackers is a bit like guessing the number of pennies or pickles in a crock, I thought it would be interesting to see what they report. At least the direction of trends should surface. No surprise, their reports differ and are a bit of a hodgepodge. They missed a lot of announced and planned sites in the mountains. Maybe their paid sites are better, but I passed on paying. Clearly, the data center invasion has arrived in Appalachia, nevertheless.
How the count was made
Cleanview, an energy data firm, keeps a public tracker of U.S. data centers. It reports the number of facilities and also their electric load in megawatts, which is the better measure. One campus in a cornfield can draw more power than a hundred server rooms in office parks.
For each state Cleanview lists the largest operating and planned projects by county. I took the 13 states that contain Appalachian Regional Commission counties and checked every listed project against the commission’s roster of 423 counties.
The result is a floor, and it should be read as one. The free pages show only the largest projects in each state. Smaller ones in Appalachian counties are missing from the tally.
What it shows
Across the 13 states, Cleanview lists 30,324 megawatts of data center capacity in operation. At least 1,493 of those megawatts are in Appalachian counties. That is about 5 percent.
The same states have 130,772 megawatts planned or under construction. At least 28,699 are in Appalachian counties. That is about 22 percent.

Source: Author’s analysis of Cleanview state listings, September 2026, matched to ARC counties. Appalachian figures count only the largest listed projects in each state and are minimums. Megawatts are reported project capacity, not electricity use.
A figure that large needs a yardstick. One thousand megawatts is a gigawatt, roughly the output of one large nuclear reactor. The comparison would be to a reactor at Palo Verde in Arizona (a giant Combustion-Engineering supplied pressurized-water reactor for AZ Public Service) or Browns Ferry (GE supplied boiling-water reactor for TVA in Alabama). These are among the largest PWR and BWR reactor units in the US and actually have nameplate capacity larger than one giggawatt.
These are capacity figures. They measure what developers say they intend to build, not electricity anyone is using. If every project proposed for Appalachian counties were built and run flat out, it would take the output of nearly 29 reactors the size of the TVA and Arizona Public Service units noted above. I can’t think of any US construction era like this except maybe the railroad era, the interstate highway era, or the nuclear plant era in its earliest iterations before plant cancellations accelerated in the eighties.
Put another way, the capacity proposed for Appalachia alone equals almost half of all the data center capacity Cleanview counts as running in the entire country today.
Three states, one grid
The boom is not spread evenly across the mountains. About 26,000 of those 28,699 megawatts are in West Virginia, Pennsylvania and Ohio.
West Virginia is the starkest case. Cleanview’s count of operating data centers in the state is zero. That is not a census, and small server rooms escape it. But it lists 11 planned, totaling 13,075 megawatts. More than 8,000 of that is a single campus proposed in Mason County on the Ohio River. Grading has begun there, and West Virginia Public Broadcasting reported in August that neighbors whose yards flooded have been selling their homes. The governor’s office has said the campus will employ 645 people on a first phase costing $69 billion, about one job for every hundred million dollars, according to the Charleston Gazette-Mail.
In Pennsylvania, eight of the nine largest planned projects are in Appalachian counties. They run from Westmoreland, Greene and Beaver in the southwest to Lackawanna and Carbon in the old anthracite fields.
In Ohio, all nine of the largest planned entries are in Appalachian counties. Eight are buildings on one site in Pike County.
All three states belong to PJM, the regional grid. Its independent market monitor says data centers drove $29.4 billion, or 46 percent, of the $63.6 billion in capacity charges from the last four auctions.
Those charges are spread across the whole grid. They reach customers far from the counties that host the projects.
Old energy ground
Look at where these projects sit and a second pattern shows.
The Pike County, Ohio, site is the former federal uranium enrichment plant at Piketon. SB Energy, the SoftBank company developing it, told the Securities and Exchange Commission the campus is designed for 17 buildings and about 10 gigawatts of power load. The Department of Energy says the company has committed to build 10 gigawatts of new generation to go with it.
In Beaver County, Pennsylvania, Aligned Data Centers broke ground this month on a campus it puts at 2 gigawatts. It stands on the grounds of the Bruce Mansfield coal plant, which closed in 2019, and it will run on its own gas-fired power.
In Luzerne County, Amazon’s buildings stand beside the Susquehanna nuclear station. Greene County’s proposal carries the name Robena, after the coal mine. Carbon County’s is called Panther Creek, after a plant that burns waste coal. Mingo County’s is on coal land.
These are communities that have already lived through one closing. They know what a promise looks like after the company that made it is gone.
Those projects also show why my count is a floor. Cleanview enters each building separately, and its free page displayed eight of the 17 at Piketon. It credited the Beaver County campus with 264 megawatts. Count both at their announced size and Appalachia’s share of the planned total reaches about one quarter.
Where the boom is not
The trackers show nothing of size in the Appalachian counties of Tennessee, Maryland or Mississippi. That does not prove those counties have no proposals, only that none ranks among their states’ largest. Tennessee’s action is in Memphis, Clarksville and Gallatin. Maryland’s is in Frederick County, just outside the region.
What the trackers miss
Virginia shows the limits of any tracker. None of the largest projects on Cleanview’s Virginia list is in an Appalachian county. The pipeline it shows is moving south and east from Loudoun County toward Richmond.
But Cardinal News has been reporting on a string of projects in the western part of the state.
Google has a permit to begin grading in Botetourt County for three buildings. Appalachian Power told state regulators the campus will draw about 300 megawatts and need $264 million in grid upgrades.
In Wythe County, which still has no zoning, TAC Data Centers plans a campus that would need more than a gigawatt. A second Wythe project comes from Solis Arx, a company its founder says was formed for that purpose.
A complex of nine buildings with its own gas plant is planned in Wise County. A developer wants three or four data centers on the old Moss No. 3 coal mine in Russell County. Pulaski County has state money to ready a site for a data center and power plant.
Eastern Kentucky shows the same gap. The tracker caught one project there, a 1,000-megawatt TeraWulf campus at an industrial park that straddles Boyd and Greenup counties.
The Kentucky Lantern keeps its own map, and it shows more. Rubix Data Centers, a subsidiary of a privately held company in Barcelona, has proposed eight buildings on the old AK Steel mill site at Russell in Greenup County. The company told the city the campus could use 2 gigawatts. That is a little more than a tenth of the most electricity Kentucky’s utilities generated in the summer of 2024.
Pikeville has a preliminary agreement with a developer for a $250 million center of 25 to 30 megawatts. In Bell County a landowner says it wants to invest billions, and the fiscal court answered with a moratorium.
And in Wolfe County, a bitcoin mine that ran for three years was reported this summer to be shutting down. Appalachia already has a data center that went quiet.
It is not the first. In 2022 Kentucky supplied nearly a fifth of the computing power behind bitcoin mining in the United States, according to Earthjustice. When the machines aged out a few years later, many operators simply left, and the Lantern has reported on the empty buildings, unpaid bills and discarded equipment they left behind.
None of these Virginia and Kentucky projects is in my 22 percent. Botetourt, the larger Wythe project and the Russell mill site alone come to at least 3,300 megawatts.
And part of Appalachia is not new to this at all. Almost all of North Carolina’s listed operating capacity is in Appalachian counties. Google has run a campus in Lenoir since 2008. Meta has been in Forest City since 2012.
Those two towns have more than a decade of experience with what the jobs, the tax base and the water use turned out to be. Any county weighing a proposal should call them.
What the numbers cannot say
Announced is not built. A planned megawatt is a press release, a zoning application or a place in a utility’s queue. Many of these projects will shrink, stall or move.
The trackers themselves do not agree. Data Center Map’s public site lists about 2,900 U.S. facilities. Pew, working from that firm’s data in February, counted more than 3,000 operating and more than 1,500 planned. Cleanview counts building by building and lists 1,296 operating and 2,132 planned. Another firm, Aterio, tracks nearly 8,000.
That uncertainty is the point. Counties are being asked to rezone land, and utilities are being asked to build lines and plants that last 40 years, on the strength of figures the industry’s own scorekeepers cannot pin down.
At a minimum, officials should ask for a named parent company, proof of site control and financing, a realistic construction schedule and a clear answer on who pays for stranded lines and plants.
One more thing stands out in the listings. Many of the 22 planned entries I found in Appalachian counties carry names most people would not recognize, among them 1778 Rich Pike LLC, Fundamental Data LLC and Bristolville 25 Developer. There is a reason the owners do not put their real names on the plants in many cases.
An unfamiliar name does not by itself show weakness or deception. It does make it important to know the ultimate owner, the financing and the guarantees. What we learn from the plant trackers is what has been learned about the data center rush all across the country: It is all happening so fast and the transparency is so low that even the specialists can’t get their arms around it all easily.
Who those companies are, and what stands behind their promises, is the next question that investigators need to address.
Jim Branscome’s recent book is “Annihilating the Hillbilly Redux: Appalachia’s Struggle Against America’s Institutions.”
Sources
Pew Research Center, “Most new data centers in the U.S. are coming to rural areas,” April 13, 2026. https://www.pewresearch.org/short-reads/2026/04/13/most-new-data-centers-in-the-us-are-coming-to-rural-areas/
Cleanview, U.S. and state data center trackers, updated September 2026. https://cleanview.co/data-centers/us
U.S. Department of Energy, “Partnership Ensures Affordable Energy, Powers AI Future at Portsmouth Site,” March 2026. https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
SB Energy Inc., Form S-1 (17 buildings at PORTS-Pike). https://www.sec.gov/Archives/edgar/data/0002133037/000162828026059639/sbenergy-sx1.htm
Keystone Newsroom, “New data center complex breaks ground in Beaver County,” September 2026. https://keystonenewsroom.com/news/infrastructure/new-data-center-complex-breaks-ground-in-beaver-county/
Data Center Dynamics, Aligned at Shippingport Industrial Park (Bruce Mansfield history), July 27, 2026. https://www.datacenterdynamics.com/en/news/shippingport-industrial-park/
Cardinal News, “New details emerge about Botetourt grid upgrades for Google data center,” Sept. 16, 2026. https://cardinalnews.org/2026/09/16/new-details-emerge-about-botetourt-grid-upgrades-for-google-data-center/
Cardinal News, “Gigawatt data center project planned for Wythe County,” June 4, 2026. https://cardinalnews.org/2026/06/04/gigawatt-data-center-project-planned-for-wythe-county/
Cardinal News, “Data center campus announced for Wythe County,” Dec. 5, 2025. https://cardinalnews.org/2025/12/05/data-center-campus-announced-for-wythe-county/
Cardinal News, “Data center complex with gas power plant planned for Wise County,” Feb. 25, 2026. https://cardinalnews.org/2026/02/25/data-center-complex-with-gas-power-plant-planned-for-wise-county/
Cardinal News, “3 or 4 data centers could be coming to a former coal mine site in Russell County,” Sept. 15, 2026. https://cardinalnews.org/2026/09/15/three-or-four-data-centers-could-be-coming-to-a-former-coal-mine-site-in-russell-county/
Utility Dive, “Data centers drove $6.3B in PJM capacity auction costs: market monitor,” July 20, 2026. https://www.utilitydive.com/news/pjm-data-centers-capacity-auction-imm-bowring/825626/
Kentucky Lantern, Liam Niemeyer, “See where data center developers are looking to build in Kentucky,” July 7, 2026, updated Aug. 16. https://kentuckylantern.com/2026/07/07/see-where-data-center-developers-are-looking-to-build-in-kentucky/
Kentucky Lantern, Liam Niemeyer, “Developer proposes hyperscale data center at former Eastern Kentucky steel mill,” July 22, 2026. https://kentuckylantern.com/2026/07/22/developer-proposes-hyperscale-data-center-at-the-site-at-former-eastern-kentucky-steel-mill/
Kentucky Lantern, Liam Niemeyer, “Crypto miners gain a friend in the White House but may be losing friends in Kentucky,” Nov. 25, 2024. https://kentuckylantern.com/2024/11/25/crypto-miners-gain-a-friend-in-the-white-house-but-may-be-losing-friends-in-kentucky/
Earthjustice, “Cryptocurrency mining in Kentucky.” https://earthjustice.org/feature/cryptocurrency-mining-kentucky
Appalachian Regional Commission, “Appalachian Counties Served by ARC.” https://www.arc.gov/appalachian-counties-served-by-arc/
Data Center Map, USA listing. https://www.datacentermap.com/usa/
Aterio, U.S. data center database, Sept. 18, 2026. https://www.aterio.io/insights/us-data-centers
PJM market monitor figure and Russell County reporting as cited in “Before the Mountains Say Yes to Data Centers” and “Who Pays When the Data Centers Go Quiet?”

Old power plant sites come with grid connections and water already in place, so of course data centers cluster there. 29 reactors of demand is a lot of leverage for these counties, which is why asking for proof of financing before rezoning is such good advice.
Hi Jim,
I want to give subscriptions to my sisters. Here are their emails:
Peggy Placier - pplacier@centurylink.net
Barbara Ervin - ervinbarbara11@gmail.com
They have both expressed interest and I will pay if you start charging.